Skip to content

Coverage

Do I need a SWPPP?

Yes, if your construction site will disturb one acre or more, and yes if it will disturb less than an acre but sits inside a larger common plan of development that will. The plan has to be written before you file the Notice of Intent, not after. Every line below carries the permit section it came from.

The three doors

What actually puts a site under the permit

A site is covered if any one of these applies. They are read out of the 2022 Construction General Permit, which governs where EPA is the permitting authority.

One acre or more of total disturbance
A construction site that will disturb one or more acres of land needs permit coverage. The acre is the project's TOTAL disturbance over its life, not the building footprint and not the area open on the day you measure it, so clearing, grading, stockpiles, haul roads, staging and laydown all count towards it.
Will disturb one or more acres of land, or will disturb less than one acre of land but are part of a common plan of development or sale (as defined in Appendix A) that will ultimately disturb one or more acres of land
Verified2022 Construction General Permit Part 1.1.2Source
Under an acre, inside a larger common plan
A site disturbing less than one acre is still covered when it is part of a larger common plan of development or sale that will ultimately disturb one acre or more. A quarter-acre lot in a subdivision is covered on the subdivision's acreage, not its own.
will disturb less than one acre of land but are part of a common plan of development or sale (as defined in Appendix A) that will ultimately disturb one or more acres of land

The operative definition of "common plan of development or sale" is in Appendix A, which is not present in the extracted source. Confirm the definition text against Appendix A before relying on edge-case interpretation.

Verified2022 Construction General Permit Part 1.1.2Source
Any size, if EPA designates the site
A site of any size that EPA has designated as needing coverage under 40 CFR 122.26(a)(1)(v) or 40 CFR 122.26(b)(15)(ii) is covered regardless of how little it disturbs.
Have been designated by EPA as needing permit coverage under 40 CFR § 122.26(a)(1)(v) or 40 CFR § 122.26(b)(15)(ii)
Verified2022 Construction General Permit Part 1.1.2Source
Who has to hold the coverage
Coverage attaches to the operator: the party with operational control over the plans and specifications, or with day-to-day control of the activities needed to comply with the permit. Where a project has more than one operator, every one of them must obtain coverage. Subcontractors generally are not operators.
The party has operational control over construction plans and specifications, including the ability to make modifications to those plans and specifications; or The party has day-to-day operational control of those activities at a project
Verified2022 Construction General Permit Part 1.1.1Source

The one people miss

A half acre lot in a subdivision is covered

Everyone knows the acre. The trigger that catches builders is the second half of the same sentence: a lot that is small on its own is covered on the acreage of the development it belongs to. The person building the lot measures the lot, and the permit measures the plan. That mismatch is why a single house on a quarter acre can need coverage while the builder is certain it does not.

will disturb less than one acre of land but are part of a common plan of development or sale (as defined in Appendix A) that will ultimately disturb one or more acres of land

The operative definition of "common plan of development or sale" is in Appendix A, which is not present in the extracted source. Confirm the definition text against Appendix A before relying on edge-case interpretation.

The half acre lot that needs a permit: the larger common plan trigger

Two different things

Permit coverage is not the SWPPP, and the SWPPP is not the permit

Coverage is the authorisation to discharge. The plan is one of the conditions attached to it, and it has to exist first.

The document is a permit condition, not the permit
All operators associated with a construction site under this permit must develop a SWPPP prior to submitting the NOI, and keep it up to date throughout coverage. Coverage is the authorisation to discharge; the SWPPP is one of the conditions you accept in return for it. Where several operators share a site they may keep one group plan, and each remains responsible for compliance.
All operators associated with a construction site under this permit must develop a SWPPP consistent with the requirements in Part 7 prior to their submittal of the NOI. 82, 83, 84 The SWPPP must be kept up-to-date throughout coverage under

Where there are multiple operators associated with the same site, they may develop a group SWPPP instead of multiple individual SWPPPs; each operator remains responsible for compliance (footnote 83).

Verified2022 Construction General Permit Part 7.1Source
It has to be reachable, not just written
A current copy must be kept at the site or somewhere easily accessible so it can be produced at an inspection or on request. Where no on-site location is available when nobody is present, a notice of where the plan is must be posted near the main entrance.
You must keep a current copy of your SWPPP at the site or at an easily accessible location so that it can be made available at the time of an on-site inspection or upon request by EPA
Verified2022 Construction General Permit Part 7.3Source
It has to keep up with the site
The plan, including the site maps, must be modified within seven days of any of the conditions in Part 7.4.1, which include the changes made in response to a corrective action. A plan that was accurate at the NOI and never touched again is not a compliant plan.
You must modify your SWPPP, including the site map(s), within seven (7) days of any of the following conditions:
Verified2022 Construction General Permit Part 7.4.1Source
Somebody has to sign it
The plan must be signed and dated by the operator's signatory in accordance with Appendix G, Part G.11. Who is allowed to PREPARE it before that signature is a separate question, and in several states the answer is not the operator.
SWPPP Certification. Your signatory must sign and date your SWPPP in accordance with Appendix G, Part G.11.

The signatory requirements themselves are in Appendix G, which is not present in the extracted source.

Verified2022 Construction General Permit Part 7.2.10Source

Sequence

The order it has to happen in

The plan is a precondition of applying, and the application carries a lead time. Working back from the first machine on site is how people find out too late.

1. Write the SWPPP
The SWPPP must be developed, consistent with Part 7, BEFORE the Notice of Intent is submitted. It is not a post-authorisation deliverable. If a plan was prepared under an earlier version of the permit it has to be reviewed and updated before the NOI goes in.
You must develop a SWPPP consistent with Part 7 before submitting your NOI for coverage under this permit.
Verified2022 Construction General Permit Part 1.4.1Source
2. File the Notice of Intent
The operator of a new site must submit a complete and accurate NOI at least 14 calendar days before construction activities commence. The NOI goes through EPA's NPDES eReporting Tool unless a Regional Office has granted a paper waiver.
must submit to EPA a complete and accurate NOI in accordance with the deadlines in Table 1 prior to commencement of construction activities

The value was read from Table 1, whose three columns interleave in the PDF text layer, so no contiguous verbatim quote spanning the full row is available; the quote is the nearest contiguous supporting text. Re-read Table 1 in the source PDF to confirm the row values.

Verified2022 Construction General Permit Part 1.4 (deadline value from Part 1.4.3, Table 1)Source
3. Wait for authorisation
Coverage begins 14 calendar days after EPA notifies you that it has received a complete NOI, unless EPA tells you the authorisation is delayed or denied. That is a second 14-day window, not the same one.
your authorization is delayed or denied.

The value was read from Table 1, whose three columns interleave in the PDF text layer, so no contiguous verbatim quote spanning the full row is available; the quote is the nearest contiguous supporting text. Re-read Table 1 in the source PDF to confirm the row values.

Verified2022 Construction General Permit Part 1.4.3, Table 1 (Permit Authorization Date column)Source
4. Have the controls in before the phase does
Installation of the stormwater controls must be complete by the time each phase of construction begins, so the plan has to be far enough along to say what those controls are and where they go.
Complete installation of stormwater controls by the time each phase of construction

Quote truncated at the extracted line break; the clause continues on the following line. Confirm the full sentence of Part 2.1.3 against the source PDF before rendering it as user-facing copy.

Verified2022 Construction General Permit Part 2.1.3Source

Two acreages, not one

The number that decides coverage is not the number that decides your deadline

Coverage is measured on total disturbance. The stabilisation deadline is measured on land open at any one time, and those are the same number only on a site that is never phased.

Table 2 of Part 2.2.14a keys the seven versus fourteen day deadline on the total amount of land disturbance occurring at any one time. Footnote 37 spells out what that means: a ten acre project that stabilises finished ground before opening more, so that cumulative disturbance never exceeds five acres, keeps the fourteen day deadline. Stabilising land frees up land. Treat the project total as the deadline number and you hand back a week the permit gave you.

When the clock starts
Stabilisation must be initiated in any area of exposed soil where construction has permanently ceased, or will be temporarily inactive for 14 or more calendar days. Immediately means as soon as practicable and no later than the end of the next business day.
The requirement to initiate stabilization immediately is triggered as soon as you know that construction work on a portion of the site is temporarily ceased and will not resume for 14 or more days
Verified2022 Construction General Permit Part 2.2.14a, Table 2 (footnote 39)Source
Five acres or less open at any one time
Complete the installation of stabilisation measures no later than 14 calendar days after stabilisation was initiated. This row explicitly covers a project that disturbs more than five acres in total but phases the work so that no more than five are open at once.
soon as practicable, but no later than 14 calendar days

This row includes sites disturbing more than five acres total over the course of a project, but that limit disturbance at any one time (i.e. phase the disturbance) to five acres or less. Stabilizing completed acreage can "free up" land for further disturbance while staying under the five-acre cap (footnote 37). Table 2 sets both columns on the same physical lines, so no single contiguous run of the PDF text layer contains this row's full sentence: the quote is therefore the longest contiguous fragment that still reads as the rule, and the full clause is 'Complete the installation of stabilization measures as soon as practicable, but no later than 14 calendar days after stabilization has been initiated.' The quote previously began 'to five acres or less', which was contiguous and verbatim but spanned the column boundary and so read as nonsense. Re-read Table 2 in the source PDF to confirm the row values.

Verified2022 Construction General Permit Part 2.2.14a, Table 2 row iSource
More than five acres open at any one time
Complete the installation of stabilisation measures no later than seven calendar days after stabilisation was initiated. Half the time, decided by a number that has nothing to do with whether you needed a permit in the first place.
Complete the installation of stabilization measures as soon as practicable, but no later than seven (7) calendar days after stabilization has been initiated.
Verified2022 Construction General Permit Part 2.2.14a, Table 2 row iiSource
Discharging to an impaired or high quality water
Where any portion of the site discharges to a sediment or nutrient impaired water, or to a Tier 2, Tier 2.5 or Tier 3 water, stabilisation must be completed within seven calendar days regardless of how much land is open. The phasing option does not buy the longer deadline back.
Complete stabilization as soon as practicable, but no later than seven (7) calendar days after stabilization has been initiated.

This accelerated deadline applies regardless of the amount of land disturbed at any one time, i.e. it removes the 14-day option that a site of five acres or less would otherwise have. Cross-referenced by Part 3.2.

Verified2022 Construction General Permit Part 2.2.14b.iiiSource

This is why the screening tool below asks for both figures. Leave the second one blank and it assumes the whole disturbed area is open at once, which can only shorten the deadline it reports, and it tells you it made that assumption rather than asserting phasing it was never told about. See how the determination is built.

Answer it for your site

Screen your site free, in this tab

It runs the same engine as the API and the paid product, here in the browser. There is no request behind it, so your acreage and location have nowhere to go.

Screen your site

Runs in your browser

Total land disturbance over the whole project, including staging and access. This decides whether you need a permit at all.

Optional. If you phase the work, the most that will be disturbed at once. Leave blank if the whole site is open together. The stabilisation deadline turns on this figure, not the total.

A half acre lot inside a 40 acre subdivision is covered even though the lot alone is under the threshold. This is the most commonly missed trigger in the permit.

Receiving water and site conditions(optional, but they change the inspection frequency)

May allow a reduced inspection frequency during the seasonally dry period.

EPA keeps permitting authority in Indian country even inside a state that runs its own programme.

No account, no card, nothing transmitted.

Who is allowed to write it

The federal permit requires the plan to be signed by the operator's signatory and imposes no preparer credential of its own. States do. We verified 7 that require a credentialed preparer outright and 6 that gate it conditionally, on acreage or on plan scope. A named role in a permit is not automatically a credential, and some of the credentials people cite belong to the reviewers rather than the authors.

Do I need a QSDEvery jurisdiction

Your state can be stricter

Everything above is the federal permit, which governs where EPA is the permitting authority. Most states run their own construction programme, and a state programme must be at least as protective as the federal one: it can be stricter and never looser. Several are, on acreage, on inspection frequency and on who signs. We hold 52 jurisdictions and we never substitute the federal figures for a state permit we have not read.

Which permit governsWhat it requires

What we are not

Where this product stops

Worth reading before you decide what a generated plan buys you.

We do not perform your inspections
The permit requires a qualified person, meaning someone who has completed the Part 6.3 training, to inspect the site on a schedule. That person walks the ground. We generate the plan and hold the inspection record; the inspection itself is yours and always will be.
You are responsible for ensuring that any person conducting inspections pursuant to this Part is a “qualified person.” A qualified person is someone who has completed the training required by Part 6.3.
Verified2022 Construction General Permit Part 4.1Source

And in a state that gates preparation on a credential, a generated document is a complete draft for that credentialed preparer to review, amend and sign. It saves them the assembly work, it does not replace their signature, and it says so on its own face. Where a state has no preparer gate, an operator can adopt it directly. None of this is legal or engineering advice.

FAQ

Common questions about needing a SWPPP

Do I need a SWPPP?

If you operate a construction site that will disturb one acre or more of land, yes. You also need one if the site disturbs less than an acre but is part of a larger common plan of development or sale that will ultimately disturb one acre or more, and you need one if EPA has designated the site regardless of its size. All three triggers are in 2022 CGP Part 1.1.2. The acre is measured on the project's total disturbance over its life, which includes grading, stockpiles, haul roads, staging and laydown, not just the building footprint.

My lot is only half an acre. Am I really covered?

If the lot is part of a subdivision, a phased commercial development or any other common plan of development or sale that will ultimately disturb an acre or more, then yes. Part 1.1.2 puts a site under the permit where it will disturb less than one acre of land but is part of a common plan of development or sale that will ultimately disturb one or more acres. This is the single most commonly missed trigger in the permit, because the person building the lot measures the lot. The operative definition of common plan sits in Appendix A, which our extraction of the permit body does not include, so confirm an edge case against Appendix A before relying on it.

Is needing permit coverage the same as needing a SWPPP document?

No, and conflating them is what produces the late scramble. Coverage is the authorisation to discharge, obtained by filing a Notice of Intent. The SWPPP is a document the permit requires you to have developed BEFORE that NOI is submitted, under Part 1.4.1 and Part 7.1. So the plan is not something you produce once you are permitted. It is a precondition of applying, and the NOI itself has to go in at least 14 calendar days before construction begins.

How long before I break ground do I need this?

Work back from three deadlines. The NOI must be submitted at least 14 calendar days before construction activities commence (Part 1.4, Table 1). Coverage then begins 14 calendar days after EPA notifies you it has received a complete NOI (Part 1.4.3, Table 1), which is a second window and not the same one. And the SWPPP has to be finished before the NOI goes in at all (Part 1.4.1). Stormwater controls must be installed by the time each phase of construction begins (Part 2.1.3).

Does the acreage that decides coverage also decide my deadlines?

No. Coverage is measured on total disturbance. The stabilisation deadline is measured on the amount of land disturbed AT ANY ONE TIME, under Table 2 of Part 2.2.14a. Footnote 37 is explicit that a project exceeding five acres in total still gets the longer 14 day deadline if it phases the work so cumulative disturbance never exceeds five acres, using stabilisation of finished ground to free up land to disturb next. Above five acres open at once the deadline halves to seven days. Our screening tool takes both numbers separately for exactly this reason, and tells you when it has had to assume an unphased site.

Can I write the SWPPP myself?

Under the federal permit the plan must be signed by the operator's signatory (Part 7.2.10), and the permit body imposes no preparer credential. Several states do. California requires a Qualified SWPPP Developer, and other states gate preparation on a licensed engineer, sometimes only above an acreage threshold. A named role in a permit is not automatically a credential, and some credentials belong to the people who review plans rather than the people who write them. Check your own state before you conclude either way.

Does the federal answer apply in my state?

Only where EPA is the permitting authority. Most states run their own NPDES construction programme, and a state programme must be at least as protective as the federal one, which means it can be stricter but never looser. Several are considerably stricter on acreage triggers, inspection frequency and who may prepare the plan. Where we have not read a state's permit we return no requirements and name the agency to confirm with, rather than substituting the federal figures.

Will a SWPPP template do?

The permit requires the document to be site specific: your site map, your receiving waters, your controls, your operators, your inspection procedures. A template is a starting shape, not a plan, and a form filled in loosely is a routine inspection finding. The plan also has to be modified within seven days of the conditions in Part 7.4.1, including changes made in response to corrective actions, so a document that was accurate at the NOI and never touched again is not compliant either.

Find out in about a minute, before it becomes a deadline

Free to screen, runs in your browser, and every requirement it returns names the permit section behind it.